From Art Halbardier, Property Director and project lead, an overview of how the next couple of weeks will look:



 Monday, 7/31, demo will occur in undercroft to provide access for speedy asbestos abatement.

Also, on Monday, 7/31, demolition on the parking lot will commence - first, prospecting for old house foundations and removing them, second stripping the area of asphalt and other impediments to the digging of wells. Duration…as long as it takes.

Parking Lot will be closed early Monday morning. A flyer will be distributed directing people to the Workforce Center, similar to the info in the last Olive Branch. Signs have been purchased which will be placed at the parking lot each Sunday from now on as a reminder.

Wednesday-Friday 8/2-4, asbestos abatement in Undercroft by Envirobate. 

Monday,8/7, horizontal boring under 31st st. for geothermal pipe, water, and electrical service to the parking lot. As soon as water service is established, geothermal drilling can begin - perhaps Tuesday or 
Wednesday. Gilbert Mechanical will begin work in boiler room.

Tuesday/8/8, demo contractor to start cutting holes in various walls and floors to provide access for duct work, pipes, etc… 


 By midweek, should be full speed ahead on all fronts. 